ASPHALT OVERLAY & RESURFACING

1.Using hydraulic sweeper's and high powered air blowers clean and remove all loose debris from surface.

2. To allow for a smooth transition after the overlay and allow for proper drainage it may be necessary to grind down along transition points, handicap ramps, dumpster pad's, catch basin's, entrance way's and exit's
ect.

OUR ASPHALT PAVING PROCESS 

Why is Asphalt the # 1 choice for Driveways, Parking lot's and road's. ?

Asphalt is strategically engineered and composed of about 95% stone, sand & gravel by weight and about 5% asphalt cement that act's like glue to hold the pavement together. It can be said that asphalt has been and still remains one of the major building blocks of our Nation. The United States of America has over 2 million mile's of roads & highway's and over 93% of them are surfaced with asphalt pavement employing thousands of people every year for maintenance and new construction. 


ASPHALT CAN BE RECYCLED AND WILL NOT RAISE YOUR TAX'S.
  

Copyright 2013. Asphalt Paving and Hot Tar Chip Sealing. All Rights Reserved.

GRADE & PAVE ON EXISTING NEW OR OLD GRAVEL SURFACE'S

Most all new or old gravel driveways and parking lot's will need to be graded, leveled and sloped for proper drainage. Some surface's have the wrong type of rock and is not a proper base #8's & #57's are a washed finishing stone that will not compact. If there is to much loose stone on top it will need to be scraped off and hauled away, we then bring in additional #304 limestone base rock and spread it as needed roll and compact.  Apply a pramitol weed killer to gravel area then string line and paint out a guide for new blacktop installation with a 2 ½ inch layer of 404 finishing course hot mix blacktop rolled and compact to a hard smooth finish with all edge's being hand tamped at a 45 degree angle for strong clean edge's. (NOTE) commercial job's are 2 inch's of 402 base course hot mix blacktop and a second layer of 404 finishing course hot mix blacktop.

Asphalt is the #1 Choice for Driveways, Parking lots, & Roads.

ASPHALT OVERLAY'S & RE-CAP'S

 As asphalt starts to age and deteriorate it becomes necessary for a new layer of asphalt (overlay/re-cap) this process extends the life of the parking lot or driveway with the old surface becoming the new base this can be done as long as the old asphalt pavement is still in reasonably sound condition, most case's we have to do some dig out and asphalt repair work, here is an example of what may need to be done

NEW CONSTRUCTION AND EXCAVATION

We offer installation of new parking area's for both commercial and residential customers the process start's by removing dirt & soil to a depth of usually 6-8 inch's in some situations we may have to dig deeper and install more base depending on what the surface is going to be used for, base rock is installed in lift's with each lift being properly compacted before final base layer prior to asphalt installation.

Excavations and Repairs before Overlay

1. Remove badly cracked and alligatored section's in surface, check the base for soft or clay area's if found dig out and remove 6-8 inch's 
2. Install #304 base rock and compact if needed.
3. Install 3
inch's of compacted #402 base course hot mix asphalt  
4. Remove parking bumper's (if any).
5. Apply an S.S.1.H tack
coattoentire surface for bonding new asphalt to old.
** IMPORTANT ** -
Tohelpinsure a level finished surface it may be necessary to do a leveling-scratch course to low lying and uneven areas as needed. This can not guarantee the elimination of low spots but will greatly reduce them.
6. Pave spread on 1 ½inch's
of compacted #404 finish course hot mix asphalt.
7. Re-install parking bumpers (if needed).
8.
Lay out & re-stripe all lines, arrow, handicap's ect
. (if needed).