Home owners and commercial parking lots some time need to add more area for extra parking, we call this a fresh cut or a new dig out's, when adding these new area's we look at feasibility of the project not only does it have to drain properly it has to be functional and after looking at the site and determining that the area can be turned into additional parking, road, roadway or ect., we will then start on the excavation by removing dirt and soil to a depth of usually 6-8 inch's in some situation's we have to dig deeper. We install a sub-base that consists of #2's or #4's and then 4-6 inch's of # 304 limestone base rock compacting the appropriate size compactor for the job.
Asphalt Overlay & Resurfacing
1.Using hydraulic sweeper's and high powered air blowers clean and remove all loose debris from surface.
2. To allow for a smooth transition after the overlay and allow for proper drainage it may be necessary to grind down along transition points, handicap ramps, dumpster pad's, catch basin's, entrance way's and exit's ect.
Excavations and Repairs before Overlay
1. Remove
badly cracked and alligatored section's in surface, check the base for
soft or clay area's if found dig out and remove 6-8 inch's
2. Install #304 base rock and compact if needed.
3. Install 3 inch's
of compacted #402 base course hot mix asphalt
Overlay
1. Remove parking bumper's (if any).
2. Apply an S.S.1.H tack coat
to entire surface for bonding new asphalt to old.
** IMPORTANT
** - To help insure a level finished surface it may be necessary
to do a leveling-scratch course to low lying and uneven areas as
needed. This can not guarantee the elimination of low spots but will
greatly reduce them.
3. Pave spread on 1 ½ inch's of compacted #404
finish course hot mix asphalt.
4. Re-install parking bumpers (if
needed).
5. Lay out & re-stripe all lines, arrow, handicap's ect. (if needed).